Iran’s Nuke Reactor Attack Spurs China; Ditches German, French PLCs For Domestic Tech At Xiluodu Dam – EurAsian Times

Report on Technological Upgrades at Xiluodu Hydropower Station and Implications for Sustainable Development Goals
Executive Summary
China has completed a comprehensive technological overhaul of the industrial control systems at the Xiluodu Dam, one of the world’s largest hydropower facilities. This initiative, which involved replacing foreign-made components with domestically engineered technology, directly supports several United Nations Sustainable Development Goals (SDGs). The transition enhances the security and resilience of critical clean energy infrastructure, fostering domestic innovation and contributing to long-term climate action objectives. This report analyzes the project’s details, its strategic rationale, and its alignment with SDG 7 (Affordable and Clean Energy), SDG 9 (Industry, Innovation, and Infrastructure), and SDG 13 (Climate Action).
Infrastructure Modernization for SDG 9: Industry, Innovation, and Infrastructure
The core of the project was the replacement of the dam’s primary control systems, a critical step in building resilient and technologically independent infrastructure as outlined in SDG 9.
Transition of Control Systems
- Previous System: The facility formerly operated using Programmable Logic Controllers (PLCs) from foreign suppliers, including Siemens (Germany) and Schneider Electric (France).
- New System: These have been fully replaced by the domestically developed NJ400 series PLC, engineered by Atekon Technology.
- Core Technology: The new PLCs are powered by Loongson 3C6000 processors, a product of China’s domestic semiconductor industry, and run on an open-source Linux operating system.
This localization of core control equipment provides a foundation for secure, stable, and independently managed operations, reducing reliance on external supply chains and enhancing national control over critical infrastructure. The same domestic PLC system has been implemented at other key national projects, including the Three Gorges and Xiangjiaba dams, demonstrating a scalable strategy for infrastructure resilience.
Advancing SDG 7 (Affordable and Clean Energy) and SDG 13 (Climate Action)
The Xiluodu Dam is a cornerstone of China’s renewable energy strategy, making the security of its operations paramount to achieving national and global energy and climate goals.
Project Significance and Energy Output
- Global Scale: Xiluodu is the third-largest hydropower station in China and the fourth-largest globally.
- Generation Capacity: With an installed capacity of 13.86 gigawatts, the station produces an average of 57.12 terawatt-hours of clean electricity annually.
- Contribution to SDGs: This output is a direct contribution to SDG 7 by increasing the share of renewable energy in the national energy mix and supports SDG 13 by displacing fossil fuel-based power generation.
By ensuring the control systems are secure from external cyber threats and supply chain vulnerabilities, the upgrade safeguards a significant source of clean energy, reinforcing the long-term viability of China’s climate commitments.
Strategic Rationale: Cybersecurity and Technological Sovereignty
The decision to replace foreign control systems is informed by global cybersecurity precedents and a broader national strategy to ensure the integrity of vital infrastructure, aligning with the principles of building strong and stable institutions (related to SDG 16).
Lessons from Historical Cyber Threats
The Stuxnet incident, which targeted Siemens PLCs to disrupt Iran’s nuclear program, highlighted the vulnerability of industrial control systems to state-level cyberattacks. This event underscored the security risks associated with foreign-supplied hardware and software in critical infrastructure sectors, including:
- Power Generation
- Water Treatment Facilities
- Petrochemical and Chemical Plants
- Transportation and Logistics
The Broader National Strategy
The upgrade at Xiluodu is part of a comprehensive government-led effort to develop domestic alternatives for key technologies. This strategy aims to mitigate risks associated with geopolitical tensions, trade restrictions, and potential supply chain disruptions. By fostering a domestic ecosystem of hardware (Loongson processors) and industrial software (Atekon PLCs), China is building a technologically sovereign foundation to support its sustainable development agenda securely and independently.
Sustainable Development Goals (SDGs) Analysis
1. Which SDGs are addressed or connected to the issues highlighted in the article?
-
SDG 7: Affordable and Clean Energy
The article focuses on the Xiluodu Dam, described as “China’s third-largest hydropower station” and the “fourth largest in the world.” Hydropower is a major source of renewable and clean energy. The dam’s significant electricity generation capacity (“13.86 gigawatts” and “57.12 terawatt-hours of electricity annually”) directly contributes to providing clean energy on a massive scale.
-
SDG 9: Industry, Innovation and Infrastructure
This is the most prominent SDG in the article. The discussion revolves around a critical piece of infrastructure (the Xiluodu Dam) and a significant technological innovation (the replacement of foreign control systems with domestically produced ones). The article highlights the national effort to “strengthen critical infrastructure,” “reduce reliance on foreign suppliers,” and develop “independent and controllable technology.” The development of Loongson’s processors and Atekon’s PLCs is a clear example of fostering domestic industry and innovation to build resilient infrastructure.
-
SDG 13: Climate Action
By focusing on a large-scale hydropower project, the article implicitly addresses climate action. Hydropower is a key alternative to fossil fuels, helping to reduce greenhouse gas emissions. The article notes that “China continues to expand its renewable energy capacity, including large-scale hydropower, wind, and solar projects,” which is a direct strategy for climate change mitigation.
2. What specific targets under those SDGs can be identified based on the article’s content?
-
SDG 7: Affordable and Clean Energy
- Target 7.2: By 2030, increase substantially the share of renewable energy in the global energy mix. The article’s subject, the Xiluodu hydropower station, is a massive renewable energy project. Its annual production of “57.12 terawatt-hours of electricity” is a substantial contribution to China’s renewable energy share.
-
SDG 9: Industry, Innovation and Infrastructure
- Target 9.1: Develop quality, reliable, sustainable and resilient infrastructure. The entire premise of the article is the effort to make the Xiluodu Dam’s infrastructure more resilient and reliable. The replacement of foreign PLCs is motivated by the need to “strengthen critical infrastructure against cyber threats,” avoid “supply chain disruptions,” and ensure “long-term safe and stable operation.”
- Target 9.5: Enhance scientific research, upgrade the technological capabilities of industrial sectors…encouraging innovation. The article details China’s success in this area, describing how Loongson Technology, which “began as part of the Institute of Computing Technology,” developed its own processors (“Loongson’s own 3C6000 processors”) and architecture (“self-developed LoongArch instruction set architecture”) to achieve technological independence. This is a direct example of upgrading technological capabilities through domestic innovation.
-
SDG 13: Climate Action
- Target 13.1: Strengthen resilience and adaptive capacity to climate-related hazards and natural disasters in all countries. While the article focuses on cybersecurity, the effort to secure a critical piece of clean energy infrastructure like a massive dam contributes to the overall resilience of the national climate action plan. A stable and secure renewable energy supply is essential for transitioning away from fossil fuels.
3. Are there any indicators mentioned or implied in the article that can be used to measure progress towards the identified targets?
-
Indicators for SDG 7
- Indicator for Target 7.2: The article provides specific quantitative data that can be used to measure renewable energy production. It states the dam has a “total installed capacity of 13.86 gigawatts” and “produces 57.12 terawatt-hours of electricity annually.” These figures are direct measures of renewable energy generation.
-
Indicators for SDG 9
- Indicator for Target 9.1: The article implies an indicator related to the resilience of critical infrastructure. The key action described is the “complete localisation of the dam’s core control equipment,” with “all such foreign-made PLCs at Xiluodu” being replaced. Progress could be measured by the percentage of critical infrastructure components that are domestically produced and controlled, reducing vulnerability to external threats.
- Indicator for Target 9.5: The article provides a concrete indicator of technological innovation and upgrading. The successful development and deployment of the “NJ400 series PLC, developed by Atekon Technology and powered by Loongson’s own 3C6000 processors” serves as a tangible outcome of investment in domestic research and industrial capability.
4. Summary Table of SDGs, Targets, and Indicators
SDGs | Targets | Indicators |
---|---|---|
SDG 7: Affordable and Clean Energy | Target 7.2: Increase substantially the share of renewable energy in the global energy mix. | Quantitative Data on Energy Production: The article specifies the dam’s total installed capacity (13.86 gigawatts) and average annual electricity production (57.12 terawatt-hours). |
SDG 9: Industry, Innovation and Infrastructure | Target 9.1: Develop quality, reliable, sustainable and resilient infrastructure.
Target 9.5: Enhance scientific research, upgrade the technological capabilities of industrial sectors. |
Localization of Critical Components: The article states the “complete localisation of the dam’s core control equipment” by replacing all foreign-made PLCs.
Development of Domestic Technology: The creation and deployment of the “NJ400 series PLC” and “Loongson’s own 3C6000 processors” built on a “self-developed LoongArch instruction set architecture.” |
SDG 13: Climate Action | Target 13.1: Strengthen resilience and adaptive capacity to climate-related hazards and natural disasters. | Implied Indicator of Infrastructure Security: The implementation of measures to secure a major renewable energy source from cyber threats, ensuring its stable operation as part of a national climate strategy. |
Source: eurasiantimes.com